General Motors Corporation
Bowling Green Assembly (Corvette Plant) Elpo Frame Project
The Elpo frame project consisted of a 10,000SF building addition, Elpo machine and conveyor system. This was a complete turn-key, design and build project with a very aggressive schedule. Gallagher-Kaiser Corporation self performed the installation of the building enclosure and ventilation system. The site / civil work, building utilities and conveyor system was subcontracted-out to approximately 15 separate companies, all managed and coordinated by Gallagher-Kaiser Corporation. The building, process equipment and conveyor systems were all installed simultaneously in order to meet the customers production schedule.
Building Addition: (New 6-Bay Building Addition 40'-0" x 241'-9”)
1. Architectural / Engineering Designs
• Surveying
• Architectural Floor Plan and Elevations
• Structural Engineering Design with Calculations
• Design Drawings for all Structural Steel
• Kentucky Licensed Structural Engineer
• Site Grading Layouts
• Structural Concrete Engineering
• Fire Alarm Engineering (Simplex)
• Electrical Load Study (Orion Engineering)
• Card Access System (Automated System Group)
• Basement Egress Engineering Study
2. Site Demolition and Relocations
• Saw Cut Asphalt
• Demo and Replace Security Fence
• Relocate and Install New Storm Sewer
• Building Demo (Conveyor Entrance and Exit Openings)
• Fire Main Relocation
3. Site and Civil Work
• Silt Fencing
• Site Security Fence
• Excavation for Foundation
• Footings, Grade Beams and Pier Foundations
• Asphalt Paving for Truck Drive Areas
• (55) "HP" Piles 20'-0"lg
• Recessed Truck Dock and Leveler Pit
• Top Soil, Seeding and Ground Cover
4. Floor and Enclosure
• 12" Concrete Slab
• Concrete Trench Drains for Process Equipment
• 4"Thk. House Keeping Pads for Storage Tanks
• Chemical Resistance Floor Coating
• Pre-Cast Concrete Side Wall Panels 7'-2"h
• Masonry Block Walls at Employee Entrance Vestibule
• Structural Steel Fabrication and Erection
• Bollards at Employee Entrance
4. Floor and Enclosure (continued)
• Double Guardrail 4'-0"h
• Wood Blocking around Roof Perimeter
• Coal Tar 4-Ply Built-Up Roof
• Metal Siding with Insulated Interior Liner
• Gutters, Downspouts, Caulking and Sealants
• Man Doors
• Eight (8) Door Employee Entrance System
• "Store Front" System at Employee Entrance
• High Speed Fabric Roll-Up Door
• Loading Dock Equipment
5. Building Electrical
• Building Copper Cable Grounding System
• Temporary Power
• 1600 AMP Power Feeder with 2500 AMP Bus Duct
• Metering Study (Orion Engineering)
• High Bay Lighting
• Exit Lights
• Emergency Egress Lights
• Outdoor Lights
• Lighting Panel
• Lighting Connection to Building EMS
• Welding Receptacles
• GFI Receptacles
• Card Access Readers
• Controlling Circuit for Dock Levelers
• Fire Alarm System,
• Voice and Data Communication
• Duct Mounted Smoke Detectors
6. Building Mechanical
• 20,000 CFM Air Handling Unit with Chilled Water Coil and PLC Controls
• Supply Air Ductwork with 1" Foil Wrap Insulation
• Building Exhaust Fans
• 2.5" Compressed Air Piping Main
• 6" Chilled Water Supply and Return Main
• Building Fire Protection Sprinkler System
• Potable Water
• Process Water
• Natural Gas
• Roof Conductors
• Process Waste Piping
Process Equipment:
• New 144'-6" ELPO Machine
• Stage #01 Elpo Paint Dip
• Stage #02 UF Spray Rinse
• Stage #03 UF Dip Rinse
• Stage #04 Fresh UF Spray Rinse
• Stage #05 Recirc. DI Spray
• Stage #06 Fresh DI Spray Rinse
• Elpo Exit Plastic Enclosure
• Inspection Deck
• Exhaust Duct to RTO
• Spang EMR Rectifier
• Ultra Filter System
• Anode Cells
• Anolyte System
Process Equipment (continued):
• DI Water Storage Tank
• Elpo Paint Storage Tanks
• Horizontal Pumps with Seal Flush System
• Exterior Platform
• Bag Filter Platforms
• Controls and Field Wiring
• Mechanical Piping
• Fire Protection Sprinklers under Drain Pans
• Deep Cleaning (Building and Process)
• Painting
• Elpo Dip Tank Lining
Conveyors:
• Conveyor 110a Install New Chain Transfer
• Conveyor 111 Install New Chain Transfer and Return Drive
• Conveyor 112 New Phosphate/Elpo Strip-Out
• Conveyor 113 New Elpo Machine
• Epoxy Coated Rail in Elpo Machine
• Conveyor Support Steel (Outside of Elpo Machine)
• Screen Guard Basket, Full Width Pan and Drain
• Drip Pan under Conveyor Rail
• Truss Reinforcements and Lead Paint Abatement (10-Trusses)